West McGee Street will blocked from Fulton Street to South Spring Street beginning Friday June 14 for almost two months. Part of South Cedar Street at McGee Street will be closed as well. The target date for reopening the streets is Friday August 9.
The city will upgrade storm water lines to 72 inches and relocate water and sewer mains as necessary. The project is intended to prevent or at least reduce the chance of flooding at Wafco Mills, the lower levels of which have been inundated after extremely heavy rains.
The McGee-Cedar intersection is at the bottom of two hills; a creek runs through the location. It was the site of a railroad line that is now being redeveloped as part of the Downtown Greenway. The storm water line replacement isn’t related to the Greenway.
“The city has wanted to do this work for years, but had challenges while the railroad was still active and under the purview of Norfolk Southern,” Dabney Sanders, project manager for the Greenway, told the College Hill Neighborhood Association in an email. “It made sense to do this work while the downtown greenway is under construction.”
The city aims to complete the project before fall classes begin at Weaver Academy and Greensboro College, which are adjacent to the work site.